Operational Pain Points
Long centralized vacuum piping causes slow suction response; even minor leaks reduce suction force, compromising positioning accuracy and detection stability.
Implementation Plan
- Install SMC ZH series vacuum generators near the suction cup to reduce vacuum build-up time.
- The vacuum pneumatic system uses KQ2 quick-connect fittings and dedicated tubing to minimize leak points.
- Configure vacuum pressure switch to monitor adsorption status in real time and trigger device alerts.
- Vacuum circuits are divided by station; a single-point anomaly does not affect other stations.
App Effects
- Faster adsorption response, more stable detection cycle
- Reduced leak points, lower vacuum pressure fluctuations
- Single-station independent maintenance reduces full-line downtime.